Module 7

Created by Xavier Lewis

Ballon framing
Wall studs run from the foundation to the roof, spaces between studs spread fire faster, required less skilled buidlers

1/18

TermDefinition
Ballon framing
Wall studs run from the foundation to the roof, spaces between studs spread fire faster, required less skilled buidlers
Platfrom framing
Universal standards for wood light frame construction on a lightweight frame used today, wall studs are separated by floor joists
Platform framing order
Found wall constructed, then first floor platform, then first floor walls, then second floor platform, then second floor walls. Platfrom-wall-paltform-wall
Platform framing advantages
Easier to handle the lumber for the walls because they are smaller, provides natural fire blocking, a and a working surface for carpenters
Platform framing disadvantages
Each platform has a thick layer of wood with horizontally running grains, which leads to larger vertical shrinkage as moisture dries from the wood which can cause stress in the finishes
Platfrom frame
Made of Nomial 2" members(1.5" in thickness), spaces 16" to 24" walls are framed with vertical studs and are connected top and bottom by horizontal plates, cellings are framed with joist
Repetitive joist
Used to fram floor or rood or ceilings connected at ends by rim borards or band joist
Sloped roofs
Framed by sloped rafter and wrist borards at the peak
Seating
Every floor, wall, and roor are seated
Most common celling members
Plywood or OSB panel
Residential basement foundation
Excavation to the necessary depth, at least below the frost line. Cast-in-place strip foundations (wall/isolated footing) are placed. Then, cast-in-place concrete foundation walls are cast on top of the footing. The concrete walls are 8" to 16" thick and 8' to 10' tall
Foundation walls
Can be of concrete machinery blocks, and two coats of parging or plaster are applied to help damp-proof the wall, and an asphaltic damp-proofing compound is applied after the second coat on the outer side of the wall
Foundation wall section
Anchor bolts cast into top of wall used to attach the foundation seal plate top and bottom of foundation wall has steel reinforcing, hooked bars, water prooding is appiled to outside of wall protection board or draingage mat outside of fonudation wall to protect resisant coating from damnging
Hooked bars
Longitudinal reinforcing bar at the bottom that connects the footing to the foundation wall and strengthens the footing
Coating and draings board
Conducts groundwater toward the bottom of the wall and the perimeter drains, perfroated drain pipe is surroned by crossed stone which is provided through out the perimeter of the wall to conduct ground water away from the foundation
Filter fabrics
are placed around crossed gravular stone to prevent gradual siting of gravel and drain pipe
When does back filling start
Only after the first floor platform is erected and can brace the wall aginst laterl soil pressure and slab on grade may be delayed untill structure is closed in
what protect the slab on grade
Should be protected from moisture in the ground by a heavy plastic paper vaper retarders