When there are multiple critical paths, we should do which of the following to crash the project? Crash a node common to all critical paths. Crash a combination of nodes that together will lower all critical paths.
Definition
Either #1 or #2 - whichever is cheapest.
New/Unreviewed
Term
Project crashing addresses tradeoffs between ___________ when it's necessary to shorten the project duration.
Definition
cost and time
New/Unreviewed
Term
Nodes with __________ must be on a critical path whereas nodes with ________ can be delayed.
Definition
zero slack; positive slack
New/Unreviewed