A __________ works left to right to determine earliest start and earliest finish times; whereas a _________ works right to left to determine latest start and latest finish times.
forward pass; backwards pass
1/13
| Term | Definition |
|---|---|
A __________ works left to right to determine earliest start and earliest finish times; whereas a _________ works right to left to determine latest start and latest finish times. | forward pass; backwards pass |
Nodes with __________ must be on a critical path whereas nodes with ________ can be delayed. | zero slack; positive slack |
When crashing a project, we should choose the node __________. | on the critical path with the lowest crash cost per period. |
A project is a series of related tasks directed toward a well-defined set of end results. Which of the following is not a typical defining characteristic of projects? | Low risk of time or cost overruns. |
_______________ is the project activity where we set goals, define the project, and develop the work breakdown structure; whereas _____________ is the project activity where we monitor costs and quality, revise the plan, and shift resources as necessary. | Project planning; project controlling |
_________ are two analytical techniques that determine start and finish times for project activities according to predecessor and successor relationships. | CPM and PERT |
When there are multiple critical paths, we should do which of the following to crash the project?
Crash a node common to all critical paths.
Crash a combination of nodes that together will lower all critical paths. | Either #1 or #2 - whichever is cheapest. |
The 50-second postcard video ________. | introduces the next country while the crew dismantles and builds a new set. |
In terms of Eurovision stage change roles, _________ works on stage right managing the floor and bringing each artist onto the stage, ____________ is stage left directing the movements of all the props on and off stage, and _______________ is the showcaller who synchronizes cues across teams? | Pernilla; Tobbe; Julia |
The Eisenhower Matrix categorizes tasks by ________. | Urgency and Importance |
____________ can enhance productivity by setting aside specific periods for high priority tasks. | Time-blocking |
Project managers do ALL of the following EXCEPT: | Set the vision, mission, and strategy for competitive advantage for the organization. |
Power skills include ________. | Leadership, communication, empathy |