Terms
13 new/unreviewed 13 total
Term
A __________ works left to right to determine earliest start and earliest finish times; whereas a _________ works right to left to determine latest start and latest finish times.
Definition
forward pass; backwards pass
New/Unreviewed
Term
Nodes with __________ must be on a critical path whereas nodes with ________ can be delayed.
Definition
zero slack; positive slack
New/Unreviewed
Term
When crashing a project, we should choose the node __________.
Definition
on the critical path with the lowest crash cost per period.
New/Unreviewed
Practice Tests
0 total
(None) Completed practice tests will show up here